The Royal Navy has ordered an urgent investigation amid claims that workers on a Trident nuclear armed submarine fixed broken bolts in the vessel’s reactor chamber using glue.
The faulty repairs on the cooling pipes aboard HMS Vanguard were found after one of the bolts fell off during an inspection, the Sun reported.
The bolt heads originally came off due to over-tightening. But, rather than replacing the damaged shafts, staff at the defence contractor Babcock implemented a quick fix and glued them back on.
Engineers at the contractor reported it as a procedural glitch after the problem was found, but did not mention the botched nature of the repair.
The faulty repairs on the cooling pipes aboard HMS Vanguard were found after one of the bolts fell off during an inspection, the Sun reported.
The bolt heads originally came off due to over-tightening. But, rather than replacing the damaged shafts, staff at the defence contractor Babcock implemented a quick fix and glued them back on.
Engineers at the contractor reported it as a procedural glitch after the problem was found, but did not mention the botched nature of the repair.
Royal Navy orders investigation into nuclear submarine ‘repaired with glue’