Posted on May 6, 2017
CPT Range Extension Platoon Leader
5.25K
5
4
1
1
0
C55f387a
Posted in these groups: Shutterstock 131444195 Signal
Avatar feed
Responses: 2
SFC Steven Harvey
2
2
0
It completely depends on 3rd Shop (or whoever is conducting the reset). It can take 72 hours to 2 weeks. One operator can replace all cables and equipment for a refit in a day. The hard part is validation and if the SAR was requested well before the process was scheduled. Best bet sir is to call the unit/shop conducting the reset and ask for a timeline, then work that into the training calendar.
(2)
Comment
(0)
CPT Range Extension Platoon Leader
CPT (Join to see)
>1 y
Thanks SSG Harvey! That sounds more realistic than what my predecessor was saying.
(0)
Reply
(0)
Avatar small
SGT Jim Arnold
1
1
0
how many in a crew? I cant see it taking more than an hour from scratch to full operation just from what I've read on the rockwell site but this eqpt is newer than me but youve got me interested in it
(1)
Comment
(0)
CPT Range Extension Platoon Leader
CPT (Join to see)
>1 y
The crew is a 3-Man team. Coming from the field, I should take about that time. But I am referring to sending the equipment away for repairs and painting. I know some repairs take longer than others, but I'm just wondering about on average, if anyone had to do this.
(1)
Reply
(0)
Avatar small

Join nearly 2 million former and current members of the US military, just like you.

close